<div>I'm preparing the launch of the 2023 grant programme and ran into the following issue with the timeline: Last year, we introduced a rule that project work has to be finalized by the end of the calendar year. This resulted in a 9 months time frame for performing the actual project work. However, this year, there would be only 6 months of project work left if we don't make any other changes. </div>
<div> </div>
<div>Timeline<br/>
2023-04-04: Call for proposals (4 weeks)<br/>
2023-05-02: QEP discussion period (2 weeks)<br/>
2023-05-16: Writing discussion summaries (1 week)<br/>
2023-05-23: Voting (2 weeks)<br/>
2023-06-06: Publication of results<br/>
--- 6 / 9 months of project work ---<br/>
2023-12-06: Deadline for follow-up reports