[GRASS-dev] [release] GRASS 7.2.1 planning
Martin Landa
landa.martin at gmail.com
Mon Mar 27 23:03:47 PDT 2017
Hi,
2017-03-03 10:28 GMT+01:00 Markus Neteler <neteler at osgeo.org>:
>>> I ask myself the question of this schedule is appropriate for point
>>> releases. Maybe 1 month between soft and hard freeze is a lot ?
>>
>> I would agree. Two/three weeks could be enough... Ma
>
>
> +1
do you agree to change it from 30 to 20 days or even 14 days [1]? Ma
[1] https://trac.osgeo.org/grass/wiki/RFC/4_ReleaseProcedure#GeneralProcedure
--
Martin Landa
http://geo.fsv.cvut.cz/gwiki/Landa
http://gismentors.cz/mentors/landa