Hi Nyall,

On Fri, 05. Feb 2016 at 15:51:04 +1100, Nyall Dawson wrote:
> * a firm plan decided and locked in BEFORE we release 2.14, so we can
>   communicate the future release plans as part of our 2.14 marketing.

On what base should a firm plan be done?   The PSC doesn't do the work - so a
timeline requires knowledge about what needs to be done and how long that takes
and who's going to work on that.

The work could already have been started.  Ok, it already started - but it's
not continuing for some reason and it's not clear to me why.

I guess it's about funding behind the scenes - but apparently that's not being
discussed openly.


Jürgen

-- 
Jürgen E. Fischer           norBIT GmbH             Tel. +49-4931-918175-31
Dipl.-Inf. (FH)             Rheinstraße 13          Fax. +49-4931-918175-50
Software Engineer           D-26506 Norden             http://www.norbit.de
-------------- next part --------------
A non-text attachment was scrubbed...
Name: signature.asc
Type: application/pgp-signature
Size: 827 bytes
Desc: Digital signature
URL: <http://lists.osgeo.org/pipermail/qgis-psc/attachments/20160205/b3fb81a1/attachment.sig>


More information about the Qgis-psc mailing list