[Qgis-psc] Fwd: Re: [Qgis-developer] Any chance we could delay freeze until after the Girona hackfest?
Andreas Neumann
a.neumann at carto.net
Wed May 18 12:33:18 PDT 2016
Hi,
I would be in favour of shifting both the feature freeze and the
release. Reducing the bug fixing period to 3 weeks won't help the
quality of QGIS. I don't think that someone relies on the absolute exact
release date anyway.
Andreas
On 18.05.2016 20:59, Richard Duivenvoorde wrote:
> On 18-05-16 17:43, Jürgen E. Fischer wrote:
>> Hi Nyall,
>>
>> On Wed, 18. May 2016 at 18:45:56 +1000, Nyall Dawson wrote:
>>> Has any decision been made here? I'm happy to go with whatever's decided,
>>> but if an extension is going to be made then I'd like to know quickly so I
>>> can plan my final days before leaving for Girona.
>> No, the discussion stalled right after it started. Do we also want to move
>> the release? The feature freeze period would be reduced to three weeks.
> Plz others chime in.
>
> For me: as this is not a LTR, I'm ok with a shorter feature freeze period.
> BUT as it is also the 'last'(??) maybe it is better to slip some weeks
> for release too, and have proper testing.
>
> BUT only if it does not give more work to the release manager (aka if
> Juergen is fine with it).
>
> Regards,
>
> Richard
>
> _______________________________________________
> Qgis-psc mailing list
> Qgis-psc at lists.osgeo.org
> http://lists.osgeo.org/mailman/listinfo/qgis-psc
More information about the Qgis-psc
mailing list