All,

OSU Facilities is doing some power work [1] on the building which houses
our data center on Saturday, January 30, 2021 between 8am to 3pm PST
(1600-2300 UTC). This will require input power to the building to be cut
off during the outage window. The data center should remain functional
during the window thanks to the generator and we do not expect any outages
on our part to happen.

[1]
https://blogs.oregonstate.edu/closurenotices/2021/01/23/1-30-2021-planned-power-outage-for-kerr-administration-building/

-- 
Lance Albertson
Director
Oregon State University | Open Source Lab
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.osgeo.org/pipermail/sac/attachments/20210125/5a0c4b49/attachment.html>
-------------- next part --------------
_______________________________________________
Hosting mailing list
Hosting at osuosl.org
https://lists.osuosl.org/mailman/listinfo/hosting


More information about the Sac mailing list