Physical movement of machines preparation

Sandro Santilli strk at kbt.io
Mon Sep 15 01:39:32 PDT 2025


On Sun, Sep 14, 2025 at 07:56:06PM -0400, Regina Obe wrote:
> 
> Regardless what order we move the other servers, I think osgeo6 physical server should be moved first.
> From what Lance mentioned, it sounded like we'd have at most a couple of hours downtime.

This should be done AFTER osgeo6 stops hosting any service,
so AFTER its containerized version takes its place, right ?

I think that's the very first step to complete, probably worth its own
thread to not mix it with the planning of physical movements.

> 2) Copy over all containers on osgeo9 to osgeo6 just before the move of osgeo9  (note at this point osgeo6 server is already at its new physical location)

Moving containers from a machine to another implies a change in the
public IP address of the service, correct ? So we should also factor
in the downtime due to DNS propagation. We should plan for it
beforetime to have a quick way to update them (lowering TTL) - doing
DNS via Ansible should help - see https://trac.osgeo.org/osgeo/ticket/3188

--strk;

  Libre GIS consultant/developer 🎺
  https://strk.kbt.io/services.html
-------------- next part --------------
A non-text attachment was scrubbed...
Name: signature.asc
Type: application/pgp-signature
Size: 659 bytes
Desc: not available
URL: <http://lists.osgeo.org/pipermail/sac/attachments/20250915/475b8093/attachment.sig>


More information about the Sac mailing list