Paul Ramsey wrote:
> On Wed, Nov 11, 2009 at 2:57 PM, Mateusz Loskot <mateusz at loskot.net> wrote:
>> For WKT Raster, I've recently started submitting tasks from our roadmap
>> as tickets on Trac, as preparation for development works, because:
>> - tickets can be assigned, then it's clear who does what
>> - tickets draw a timeline of development, past and future
>> - tickets archive discussion on particular topic on single page,
>>  it's easier to keep it focused, so clear to reader and maintainer
>> - tickets directly link to events in source tree
>> Does the sanity thing mean we should stop using Trac for the purposes
>> described above?
> 
> No, because you are creating tickets that are going to be assigned,
> completed and closed. These are "wouldn't it be nice if..." tickets.

Understood.

> I think having a FUTURE milestone might help. I want to be able to
> take a numbered milestone and *close* all the tickets and then
> release. Instead I have to re-negotiate the same set of tickets that
> are of low priority each and every time and push them forward and
> forward and forward. I'd rather have people argue for putting
> particular tickets *into* a milestone than have to argue about moving
> tickets *out*.

Understood again. Good idea this FUTURE milestone.