This is my report for Week 8 (July 2 - July 8):


*What did you get done this week?*

   - Full implementation of pgr_directedChPP.

Details can be found in [1].
Set of pull requests can be found in [2].


*What do you plan on doing next week?*

   - Fix bugs and improve code.

Details of possible sub tasks can be found in [3]


*Are you blocked on anything?*
No, at the moment I’m not blocked.

The wiki page can be found in [4]
The repository can be found in [5]

[1]
https://github.com/pgRouting/pgrouting/wiki/GSoC-2018-Minimum-cost-flow-and-ChPP#week-8
[2]
https://github.com/pgRouting/pgrouting/pulls?q=is%3Apr+author%3AXJTUmg+is%3Aclosed+milestone%3A%22GSoC+2018+Official+Coding+Period+Phase+1%22
[3]
https://github.com/pgRouting/pgrouting/wiki/GSoC-2018-Minimum-cost-flow-and-ChPP#week-9
[4]
https://github.com/pgRouting/pgrouting/wiki/GSoC-2018-Minimum-cost-flow-and-ChPP
[5] https://github.com/pgRouting/pgrouting/tree/gsoc/ch_postman

Best regards,
Maoguang Wang
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.osgeo.org/pipermail/soc/attachments/20180708/776c87b9/attachment-0001.html>


More information about the SoC mailing list